Art Azarbarzin: In December 2009, we had our CDR and shortly after that we started the manufacturing process

2
00:00:28.410 --> 00:00:32.420
for all the components of GPM.

3
00:00:32.440 --> 00:00:36.440
After about a year and a half, we started putting the spacecraft structure

4
00:00:36.460 --> 00:00:44.570
together and went through the qualification of the structure and, the step after that was installing the harness.

5
00:00:44.590 --> 00:00:48.720
The harness for a spacecraft is a component which

6
00:00:48.740 --> 00:00:56.860
basically all the wires that we put on the spacecraft that connects all the boxes together with the connections at each end.

7
00:01:00.920 --> 00:01:08.960
Candace Carlisle: We started the integration of the observatory with the delivery of the two instruments: the GPM Microwave Imager

8
00:01:08.980 --> 00:01:13.000
and the Dual-frequency Precipitation Radar in early 2012.

9
00:01:13.020 --> 00:01:21.030
These were then integrated onto the spacecraft, and we checked everything out to make sure everything works

10
00:01:21.050 --> 00:01:29.150
culminating with a Comprehensive Performance Test in October of 2012.

11
00:01:29.170 --> 00:01:37.270
Before we launch any spacecraft we do a very lengthy and detailed set of tests to make sure

12
00:01:37.290 --> 00:01:45.340
that the spacecraft is going to survive all the environments that it's going to see during the launch and on orbit.

13
00:01:45.360 --> 00:01:49.370
Art: The test program for the observatory is pretty rigorous and that's because

14
00:01:49.390 --> 00:01:53.380
once we get into space, we have only one shot at this.

15
00:01:53.400 --> 00:02:01.480
Candace: The next thing we do is make sure that everything's still working after the full suite of environmental tests.

16
00:02:01.500 --> 00:02:05.540
So we do deployments of the solar arrays and the

17
00:02:05.560 --> 00:02:09.650
GMI and the High Gain to make sure those still work just the same way they

18
00:02:09.670 --> 00:02:17.760
did before we went into environments. Art: The GPM Observatory is about 3900 kilogram spacecraft, fully loaded.

19
00:02:17.780 --> 00:02:25.830
Very large spacecraft. And the larger the satellite is, just the logistics of moving them from one location

20
00:02:25.850 --> 00:02:33.880
to another is much more complicated than when you're dealing with a small satellite. That's why spacecrafts or

21
00:02:33.900 --> 00:02:42.110
observatories like GPM Core Observatory take longer for us to complete the manufacturing and testing

22
00:02:42.130 --> 00:02:46.170
and all the environmental testing we need to do at the end.

23
00:02:46.190 --> 00:02:50.310
Candace: Here at Goddard we have about 300 people working on GPM.

24
00:02:50.330 --> 00:02:54.360
About 100 civil servants and about 200 contractors.

25
00:02:54.380 --> 00:03:02.510
That, in addition to a number of people at the Japan Aerospace Exploration Agency who worked on the DPR instrument

26
00:03:02.530 --> 00:03:10.580
and at Ball Aerospace who worked on the GPM Microwave Imager instrument. Art: Once we complete the GPM Core

27
00:03:10.600 --> 00:03:18.630
Observatory testing inside our high bay, we get the spacecraft prepared for shipment. Then our next step

28
00:03:18.650 --> 00:03:22.780
is to transport it to Andrews Air Force Base and install it

29
00:03:22.800 --> 00:03:26.840
on the C-5 and then take it to Tanegashima Island.